Clubhouse Renovations-Progress to Date (2/21/2024)

Foundation Renovations

Here’s where we are with the LISE Clubhouse renovation process – work is once again underway. After an interlude to determine if re-engineering was required when bedrock was determined to be deeper than originally anticipated, the plan has been revised to compensate for actual conditions. The appropriately sized rebar is sourced and the foundation work can be resumed.

Electrical Updates

Good use has been made of the down-time in the foundation renovation – an electrician was brought in to bring our aging power panel, wiring and lighting up to current standards.

Tim Robison, Operations Chair, sends this update on the electrical work – “Electrical work, including cleaning up the electrical panel, finishing install of the new LED overhead lights, replacing electrical outlets, including GFCI outlets outside and in the kitchen have all been completed.  A permanently wired smoke and fire detector also was installed.  Exterior Lights are next; all will be either night sensors or motion sensor LED lights.  A lot of the outside lights have not been working in recent memory - including the ones mounted to trees.  They will all be working soon.”
 
This should result in a much safer experience when the Clubhouse hosts evening activities. The upgrades to the lighting, addition of the large-screen Media cart and the soon-to-be upgraded furnace should all combine to bring our beloved Clubhouse into the 21st century with comfort and style.