February 21-March 24, 2023 Operations Report

Kevin Southworth, Operations Manager

During this period:

  • Installed new service connection on Scenic Ave.

  • Flushed section 3

  • Work truck preventative maintenance

  • Installed Clark Circle sign

  • Excavated geotech study pits at proposed new WTP site

  • Completed SAM registration

Upcoming Projects:

  • Continue leak detecting and distribution repairs

  • Install dog waste posts

  • Replace anodes on docks

  • Remove lake weeds from swim lake

February 2023 Water Usage (in gallons)

From storage tanks 506,400 Chlorine monitoring feed (0.178 gpm) 7,177
Net to distribution 499,223
Flushing 3,000 Residential meters 225,777
Unaccounted for water 270,446 Percentage of loss 54% Average gallon per minute loss 6.7

Lab Results from this Period (PDF)