July 18-August 15, 2025 Operations Report
/Nick Kluge, Operations Manager
During this period:
● Pressure survey on Dogwood
● Restocked WTP supplies
● Grounds keeping
● Continue progress on water adjudication process
● Located and repaired leak on Beach Ave
● Cleaned up tree wind fall
● Relocated customer service connection on Beach in coordination with Granite project
● Ordered water main repair parts
● Clubhouse maintenance and cleaning
● Kevin covered 2 days for staff
● Wilson Engineering meeting to discuss low pressure zone mitigation
● Draft work on Water Pressure Adequacy policy
● New tables assembled for Clubhouse
● Draft work for new hardness field test kit operator procedures
● Monthly and bi-monthly dam inspections
● Settling pond quarterly maintenance
● Weekly DOE discharge monitoring tests
● Monthly distribution system flushing
● Collected water samples for lab analysis for DOH monthly quality compliance
● Cleaned and serviced online analyzers
● Weekly customer leakage survey
● Monthly DOH meeting
● Tested the WTP generator
● Town supply runs and junk removal
Upcoming Projects:
● Locate and confirm condition of the decommissioned old raw supply pipe
● Distribution refurbishment on Dogwood for water pressure adequacy
● Install signage at Swim lake
● Collect additional bids for community road repairs
● Install fish cages in the lakes
● Electrician to be contracted for reservoir tank level sensors
● Repair Cabana bathrooms
● Install Marina cameras
● Install new distribution sampling stations
● Replace old standpipe valves
● Reservoir floating dock engineering drawings review and permit application
July 2025 Water Production/Usage (in gallons)
Total Water Produced 537,800 Chlorine monitoring (0.178 gpm) 7,946
Flushing 3,000
Metered Usage 407,290
Other (Chlorine residual testing, BW) 2,325 Authorized Consumption 420,561
System Leakage 117,239
Percentage of loss 21.8% Average gallon per minute loss 2.6