September 27-October 25, 2025 Operations Report
/Nick Kluge, Operations Manager
During this period:
●Pond weed removal
●Cross Connection Control Program development
●Continued pressure zone surveying and data analysis
●Completed Beach Ave water main repairs
●Identified and repaired service main leak
●Cabana closed and winterized (October 1st-April 30th)
●Installed new water service connection
●SWSMP task review
●Picked up treatment chemicals from town
●Grounds keeping (mowing, weed eating, clearing ditches, street sweeping)
●Monthly and bi-monthly dam inspections
●Weekly DOE discharge monitoring tests
●Monthly distribution system fl ushing
●Water samples for DOH monthly quality compliance
●Cleaned and serviced online analyzers
●Weekly customer leakage survey
●Monthly DOH meeting
●Tested the WTP generator
●Ongoing discussions with Ram regarding the decommissioning of the old raw water line
Upcoming Projects:
● Winterize Clubhouse. Water turned off (December 1ˢᵗ-March 1ˢᵗ)
● Update SWSMP
● Install new fish cleaning station on marina dock
● Replace sampling stations on Cedar Ave, and at the Island/Beach intersection
● Replace bent standpipe on Island Dr
● PRV vault replacement (seeking bids)
● Community road repairs (seeking bids)
● Install fish cages in the lakes
● Refurbish the Cabana bathrooms
● Install Marina cameras
● Replace old standpipe valves
● Reservoir floating dock
September 2025 Water Production/Usage (in gallons)
Total Water Produced 405,400 Chlorine monitoring (0.178 gpm) 7,690
Flushing 3,000
Metered Usage 289,470
Other (Chlorine residual testing, BW) 2,250 Authorized Consumption 302,410
System Leakage 102,990
Percentage of loss 25.4% Average gallon per minute loss 2.38