March 21-April 22, 2026 Operations Report

Nick Kluge, Operations Manager

During this period:

  • Carol Lane lake sign installed

  • SWSMP document drafting

  • Troubleshooting and investigating fi lter performance and effi ciency

  • Research treatment techniques

  • Backhoe preventative maintenance

  • Mowing and grounds maintenance

  • Preparing docks for launch

  • Boat launch ramp maintenance

  • Replace broken swim lake park bench

  • Removed failed mixing pump from reservoir tank #2

  • Cabana remodel underway

  • Raw water line decommissioning site visit and planning

  • Huizenga conversations on road repairs

  • Stormdrains inspected and cleared of debris

  • Mower maintenance performed

  • Distribution components inspections

  • Monthly/bi-monthly/and annual dam inspections and reporting

  • DOE discharge monitoring tests

  • Monthly distribution system flushing

  • Water samples submitted for DOH monthly quality compliance

  • Cleaned and serviced online analyzers

  • Weekly customer leakage survey

  • Tested the WTP generator

Upcoming Projects:

➢ Replace mixing pump in Tank #2

➢ Decommission old raw water line under the dam

➢ Launch docks (end of April-first week of May)

➢ Replace sampling stations on Cedar Ave, and at the Island/Beach intersection

➢ Replace bent standpipe on Island Dr

➢ PRV vault replacement (seeking bids)

➢ Install fish cages in the lakes

➢ Install Marina cameras

➢ Replace old standpipe valves

➢ Reservoir floating dock

March 2026 Water Production and Usage (in gallons)

Total Water Produced 383,000 Chlorine monitoring (0.178 gpm) 7,946
Flushing 3,000
Metered Usage 217,916
Other (Chlorine residual testing, BW) 2,325 Authorized Consumption 231,187
System Leakage 151,813
Percentage of loss 39.64% Average gallon per minute loss 3.40