April 23-May 31, 2026 Operations Report
/Nick Kluge, Operations Manager
During this period:
DOE raw water line meeting
SWSMP & Ops Manual editing
Troubleshooting and investigating filter performance and efficiency
Boat launch ramp maintenance
Launched docks
Installed flushing adaptor for Beach Ave
Distribution components inspections
Backhoe preventative maintenance
Received order of gravel
Ordered new mixing pump for reservoir tank #2
Installed bird & bat houses at swim lake
Received second estimate for road repairs
Mowing and grounds maintenance
Stormdrains inspected and cleared of debris
Grounds keeping tool maintenance performed
Monthly/bi-monthly/and annual dam inspections and reporting
DOE discharge monitoring tests
Monthly distribution system flushing
Water samples submitted for DOH monthly quality compliance
Cleaned and serviced online analyzers
Weekly customer leakage survey
Tested the WTP generator
Upcoming Projects:
➢ Road repair patch and seal
➢ Replace mixing pump in Tank #2
➢ Decommission old raw water line under the dam
➢ Replace sampling stations on Cedar Ave, and at the Island/Beach intersection
➢ Replace bent standpipe on Island Dr
➢ PRV vault replacement (seeking bids)
➢ Install fish cages in the lakes
➢ Install Marina cameras
➢ Replace old standpipe valves
➢ Reservoir floating dock
April 2026 Water Production and Usage (in gallons)
Total Water Produced 348,800 Chlorine monitoring (0.178 gpm) 7,690
Flushing 3,000
Metered Usage 242,800
Other (Chlorine residual testing, BW) 2,250 Authorized Consumption 255,740
System Leakage 93,060
Percentage of loss 26.7% Average gallon per minute loss 2.15