September 18-October 17, 2026 Operations Report
/Nick Kluge, Operations Manager
During this period:
Maintenance on X570 mower
Pressure washing at Cabana
Collected rollers for dock removal
Removed rotting guard rail by WTP
Power tool maintenance
Responded to DOH comments in SWSMP rework
Removed wind fall from roadways
Chlorine injector inspection and service
Removed docks
Removed debris from Marina
All gutters and downspouts cleared
Holiday Lake grounds keeping
Storm drains inspected and cleared of debris
Response sent to DOH from sanitary survey finding
Operations Manual updates – Filter Maintenance Program
Located service main leaks at the Marina and on Beach Ave
Monthly/bi-monthly/and annual dam inspections and reporting
DOE discharge monitoring tests
Monthly distribution system flushing
Water samples submitted for DOH monthly quality compliance
Cleaned and serviced online analyzers
Weekly customer leakage survey
Tested the WTP generator
Upcoming Projects:
➢ Reduce distribution losses
➢ Replace sampling stations on Cedar Ave, and at the Island/Beach intersection
➢ Replace standpipes and valves (Baker, Beach, Island, Marina)
➢ PRV vault replacement
➢ Install fish cages in the lakes
➢ Install Marina cameras
➢ Replace old standpipe valves
➢ Reservoir floating dock
September 2026 Water Production and Usage (in gallons)
Total Water Produced 422,200 Chlorine monitoring (0.178 gpm) 7,690
Flushing 3,000
Metered Usage 227,650
Other (Chlorine residual testing, BW) 2,250 Authorized Consumption 240,590
System Leakage 181,610
Percentage of loss 43.02% Average gallon per minute loss 4.20