September 18-October 17, 2026 Operations Report

Nick Kluge, Operations Manager

During this period:

  • Maintenance on X570 mower

  • Pressure washing at Cabana

  • Collected rollers for dock removal

  • Removed rotting guard rail by WTP

  • Power tool maintenance

  • Responded to DOH comments in SWSMP rework

  • Removed wind fall from roadways

  • Chlorine injector inspection and service

  • Removed docks

  • Removed debris from Marina

  • All gutters and downspouts cleared

  • Holiday Lake grounds keeping

  • Storm drains inspected and cleared of debris

  • Response sent to DOH from sanitary survey finding

  • Operations Manual updates – Filter Maintenance Program

  • Located service main leaks at the Marina and on Beach Ave

  • Monthly/bi-monthly/and annual dam inspections and reporting

  • DOE discharge monitoring tests

  • Monthly distribution system flushing

  • Water samples submitted for DOH monthly quality compliance

  • Cleaned and serviced online analyzers

  • Weekly customer leakage survey

  • Tested the WTP generator

Upcoming Projects:

➢ Reduce distribution losses
➢ Replace sampling stations on Cedar Ave, and at the Island/Beach intersection
➢ Replace standpipes and valves (Baker, Beach, Island, Marina)
➢ PRV vault replacement
➢ Install fish cages in the lakes
➢ Install Marina cameras
➢ Replace old standpipe valves
➢ Reservoir floating dock

September 2026 Water Production and Usage (in gallons)

Total Water Produced 422,200 Chlorine monitoring (0.178 gpm) 7,690
Flushing 3,000
Metered Usage 227,650
Other (Chlorine residual testing, BW) 2,250 Authorized Consumption 240,590
System Leakage 181,610
Percentage of loss 43.02% Average gallon per minute loss 4.20